Timeline Electric - Temporary electric service generally takes just a few days if appropriate facilities exist at the project site. If your municipality does not inspect temporary service, your electrician will submit a notarized wiring affidavit. Permanent electric service generally takes two to four weeks after we receive the following items (provided you have prepared your site for installation):
Multifamily and commercial/industrial projects require an additional two to four weeks for engineering work. Your electrician must request approval from the local electrical inspector. The inspector then provides us with the electrical inspection permit for permanent service. Natural gas - Gas service takes about three weeks after we receive the application and the site is prepared for your service installation. Starting service Your gas service, however, cannot be turned on until:
|
|||||||